 | 30% schematic design progress meeting – April 13
 | 
| o
 | 60% design development progress meeting - May 11
 | 
| o
 | 90% construction documents progress meeting – June 14
 | 
| o
 | 100% construction documents submittal – July 14
 | 
| o
 | Bidding Period – July 27, 2017 – August 24th, 2017
 | 
| o
 | Major Construction start date - October 1, 2017 
 | 
| §    
Fall 2017-Utilities/Spring 2018 – remainder of improvements 
 | 
| §    6th & Main cannot be under construction for ACD Festival and Fair
 | 
| §    
ACD Festival August 30th – September 6th
 | 
| §    
Fair September 24th – September 30th 
 | 
| o
 | Substantial completion – June 30, 2018
 | 
| ·    
Construction Documents Drawings overview, page turn and specific design elements to discuss
 | 
| o
 | 60% Plan Review Comments addressed. 
 | 
| o
 | Horizontal and Vertical Control Plan added 
 | 
| o
 | Demolition
 | 
| o
 | Dimensional
 | 
| §    
ADA parking space added
 | 
| §    
Snow route and loading area signs removed to reduce amount of signage
 | 
| §    
Cricket’s access and dumpster 
 | 
| ·    
Two solutions have been identified
 | 
| o
 | Solution 1: PNC bank allows access from the east drive and dumpster and transformer stay in current location
 | 
| o
 | Solution 2: Cricket’s shares a dumpster with the 6th & Main business or the dumpster remains in its current location allowing a driveway to be installed. The transformer would stay within the right of way in a reduced landscape island. Preliminary discussions with the James group have taken place and they are open to this. 
 | 
| o
 | Grading
 | 
| §    
Sidewalk on Main Street – existing sidewalk cross slope exceeds 2% ADA maximum
 | 
| ·    
Asphalt wedge has been increased to eliminate the 7” and 8” curb height
 | 
| o
 | Utility plan & profile
 |